This week (week of 6/14):
- Front Street to Coulee Road:
- Prepare for restoration of the trail in front of the wastewater treatment plant
- Set up the temporary pedestrian crossing movements at Coulee Road intersection traffic signal
- Shift traffic over to the outside lanes, and begin pavement patching on inside lanes
- Coulee Road to Vine Street:
- Finish concrete work on west side of the street
- Vine Street to Lake Mallalieu:
- Water main construction between River Street and Division Street
- Sanitary sewer main construction between St Croix Street and Division Street
- Storm sewer construction between Myrtle Street and St Croix Street
- Grading between Myrtle Street and St Croix Street
- North Hudson:
- Storm sewer between Monroe Street and Michaelson Street
Next week (week of 6/21):
- Front Street to Coulee Road:
- Paving trail in front of wastewater treatment plant
- Pedestrian ramps at Coulee Road intersection
- Work on Leverty Financial parking lot restoration
- Coulee Road to Vine Street:
- No work (see explanation below)
- Vine Street to Lake Mallalieu:
- Finish sanitary sewer between St Croix Street and Division Street
- Begin water and sanitary sewer services between St Croix Street and Division Street
- Finish grading between Myrtle Street and St Croix Street
- Pour curb between Myrtle Street and St Croix Street
- North Hudson:
- Grading between Monroe Street and Michaelson Street
For more information, please see the document below.
Update 6/14/21 (PDF)