[ARCHIVED] 2013 Street Improvement Project Update

Here is the 2013 Street Construction Schedule Update (Starting on Saturday, October 5, 2013) as provided by the Foth Engineering, the City's engineer.

Hanley Road
The Contractor plans to pave on Saturday; however, this could change based on the weather. The earliest they would start is around 9:00 a.m.
The paving will continue on Monday and Tuesday, as needed.

O’Keefe Road
On Tuesday the Contractor will place an asphalt wedge along the shoulders.
Concrete work will continue on Monday, Tuesday and Wednesday.
Pave asphalt patches later in the week.
Pave asphalt surface course at the end of the week.

Gateway Area and Center Drive
Continue with concrete work on Monday and Tuesday.
Pave asphalt patches later in the week.
Pave asphalt surface course at the end of the week.

Crestview Drive
Continue to work on the removal and replacement of concrete items.
Work on the repairs for the storm sewer structures and sanitary sewer structures.